Thales Air Defence


Client : Thales Air Defence - Belfast Cleanroom

 

Value : £85,000.00

 

Duration : 24 weeks

 

Completion Date : August 2016

 

Consultant : Stephen Clarke Consulting Ltd

 

KMDL Project Manager : K Maginty

 

Description of Work : Electrical Services to new Cleanroom Facility including electrical works associated with the New Scanner unit. Works carried out during the normal operation of a busy factory unit.

 

The Electrical services involved the following systems:-

 

* Mains & Sub Power Distribution

* Data Cabling Installation

* General & Emergency Lighting

* Mechanical Services Wiring

* General Purpose Power

* Door Access System Installation

* Fire Alarm Installation

* Air Conditioning System

* CCTV Installation

 

Email Icon Email us: office@kmdlengineering.com

 

patconstruction lineapproaved contractorSpark Safe