Alterity Investments
Client : Alterity Investments
Value : £100,000.00
Duration : 16 weeks
Completion Date : Febuary 2017
Consultant : AECOM
KMDL Project Manager : K Maginty
Description of Work : KMDL Engineering (NI) Ltd carried out the Electrical Services installation in the refurbishment & Extension to Callender Street Belfast Offices. The Work was complete in 16 weeks under the supervision of AECOM Electrical Consulting Engineers.
The Electrical services involved the following systems:-
* Mains & Sub Power Distribution
* General & Emergency Lighting
* Mechanical Services Wiring
* External Lighting Installation
* TV Installation
* General Purpose Power
* Door Access System Installation
* Fire Alarm Installation
* Disabled Refuge Installation
* Disabled Toilet Alarm System
* Air Conditioning System